Project Description

Description:

When a series of roofs at Brentwood School began to fail, BriggsAmasco was appointed to deliver a clean, robust and long term solution. Utilising a highly-skilled team, the company installed a complete roofing and insulation system in just 12 weeks to bring the building up to the very latest waterproofing and performance standards.

As Principal Contractor on the project, BriggsAmasco was appointed to install new waterproofing and insulation on five different levels across the school’s Courage Hall building. To improve thermal performance and ensure complete waterightness, the company specified a new 1,200m2 roofing system comprising 120mm thick Thermoroof PIR insulation and a Sarnafil G410-EL waterproofing membrane.

Location:

Essex

Approx. Area:

1,200m2

Specification: